RIVER BASINS STATUS
Pampanga Non-Flood watch
Agno Non-Flood watch
Bicol Non-Flood watch
Cagayan Non-Flood watch
Pasig-Marikina Non-Flood watch
Abra Under-Construction
Cagayan De Oro Under-Construction
Ilog-Hilabangan Under-Construction
Jalaur Under-Construction
Panay Under-Construction
Tagum-Libuganon Under-Construction
DAMS/RESERVOIR (SUB BASIN) STATUS
Angat Non-Flood watch
Binga-Ambuklao-San Roque Non-Flood watch
Pantabangan Non-Flood watch
Magat Non-Flood watch
General Flood Advisory
Metro Manila Flood Monitoring
  • Location

  • Select Scale First
1:10,000 Scale Map
1:15,000 Scale Map
1:50,000 Scale Map
Dam Information
Dam Water Level Update
December 31,2017 06:00:00 am
Dam Name Observation Time & Date Reservoir Water Level (m) Water Level Deviation Normal High Water Level (m) Deviation form ? Rule Curve Elevation (m) Deviation from Rule Curve (m) Dam Release
Caliraya Dec 31, 2017 - 06:12 am 200.00 -87.49 0.00 0.00 0.00 0.00 -
Magat Dec 31, 2017 - 06:12 am 200.00 8.05 193.00 7.00 190.97 9.03 -
Pantabangan Dec 31, 2017 - 06:12 am 200.00 -2.29 221.00 -21.00 210.07 -10.07 -
San Roque Dec 31, 2017 - 06:12 am 200.00 -70.64 280.00 -80.00 268.96 -68.96 -
Binga Dec 31, 2017 - 06:12 am 200.00 -373.45 575.00 -375.00 574.00 -374.00 -
Ambuklao Dec 31, 2017 - 06:12 am 200.00 -550.19 752.00 -552.00 752.00 -552.00 -
La Mesa Dec 31, 2017 - 06:12 am 200.00 121.91 80.15 119.85 0.00 0.00 -
Ipo Dec 31, 2017 - 06:12 am 200.00 99.03 101.00 99.00 0.00 0.00 -
Angat Dec 31, 2017 - 06:12 am 200.00 -12.30 212.00 -12.00 204.75 -4.75 -
Dam Location Map
Dam Operation

BACKGROUND

Recognizing the need for operational flood forecasting and warning system to help mitigate losses of life and property brought about by annual occurrences of flooding, the Government piloted a Flood Forecasting and Warning System (FFWS) for the Pampanga River Basin in 1973. The project was established with the financial assistance from the Government of Japan, the warning system proved effective than it led to the establishment of a similar system covering Agno, Bicol and Cagayan River Basins.

In April 1983, the Flood Forecasting and Warning System for Dam Operation (FFWSDO) project was conceived. The project was meant to prevent the occurrence of similar incident (i.e. Angat Dam) which result to the imprecedented flood heights that caused destruction and deaths downstream of the dam.

Implementation of the project was done stages (Phases I and II). Phase I, for Angat and Pantabangan Dams. Was completed in July 1986, was funded under the 10th Yen Loan Package from Japan Overseas Economic Cooperation Fund (OECF).

For Phase II, implementation was started last January 1990 and was fully completed by the on set of the rainy season in 1992. The major components of Phase II are the establishment of the PAGASA Data Information Center, flood forecasting and warning systems, flood forecasting and warning system at dam offices, hydrological stations, warning posts, repeater stations and monitoring stations.

The project was implemented with the National Power Corporation (NPC) and the National Irrigation Administration (NIA) as cooperating agencies and the Philippine, Atmospheric, Geophysical and Astronomical Services Administration (PAGASA) as the lead agency.

THE PROJECT

The Flood Forecasting and Warning system for Dam Operation (FFWSDO) aims at the establishment of telemetered flood forecasting warning system that will provide the necessary information for the safe and cost effective operation of the existing five major dams in Luzon and to forewarn the people in the flood plains downstream of these damsites of the impending release of impounded water through spillways during typhoons. Phase I, involves the establishment of a FFWS covering Angat and Pantabangan watershed areas, while Phase II, involves the establishment of a FFWS covering Magat and Binga/Ambuklao watershed areas.

The Agencies directly involved in the implementation of the project such as NPC and NIA are dam authorities who operate and manage the Angat and Binga/Ambuklao Dams and Pantabangan and Magat Dams respectively amd the Philippine Atmospheric, Geophysical and Astronomical Services Administration (PAGASA) through its Flood Forecasting Branch which operates the flood forecasting warning systems. Monitoring agencies are the Department of Public Works and Highways (DPWH), Office of Civil Defense (OCD) and the National Water Resource Board (NWRB).

The complete FFWSDO has the following basic system and components:

  1. Real-time telemetering system consisting of the optimum number of rainfall and water level gauging stations

  2. Real-time processing computer system to forecast flood water inflow to the reservoir based on the telemetered rainfall data;

  3. Flood warning system with warning disseminationfacilities and supervisory control stations in dam offices;

  4. Overall supervisory system for the operation of the above system in the respective Central Offices of NPC, NIA, and PAGASA;

  5. Monitoring system which will allow exchange of necessary information among the participating agencies in flood control and other related activities; and

  6. Telecommunication system which provide the means for continuous information flow for the operation of the above system.

The project will result in the effective use of the hydrological data and information for the efficient operations and management of reservoirs and ensure the optimum use of the impounded water for power generation, irrigation, flood control and domestic water supply, the mitigation of flood damages, particularly loss of human lives, by timely and adequate warnings of impending release of impounded water through the spillways.

FACILITIES

The Flood Forecasting and Warning System for Dam Operation consists of a network of telemetered gauging stations, warning stations, supervisory control offices of damsites linked with supervisory centers in Central Offices of NPC, NIA and PAGASA. The project’s major facilities are as follows;

FACILITIES NUMBER
a. Center at PAGASA 1
b. Center at NPC and NIA 2
c. Rainfall gauging station 19
d. Waterlevel gauging station 7
e. Fixed warning station 69
f. Mobile warning station 24
g. Repeater station 13
h. Reflector station 2
i. Monitor station 3

The Flood forecasting and Warning System for Dam Operation is composed of the following four major sub-system, namely;

SUB-SYSTEM

Each of the sub-system are composed of the following components:

NAME OF DAM AREAS COVERED
PHASE 1
A. ANGAT DAM NORZAGARAY TO PLARIDEL
B. PANTABANGAN DAM RIZAL TO CABANATUAN CITY
PHASE II
A. MAGAT DAM MARIS DAM TO NAGUILIAN
B. BINGA/AMBUKLAO DAM SAN ROQUE TO CARMEN

TELEMETERING SYSTEM

The telemetering system is composed of rain and water level gauge stations (installed in selected places in dam watersheds) and radio telecommunication system for transmission of data.

In each damsite, at least three raingauge stations are installed in selected locations considered appropriate based on hydrological considerations, radiowave propagation and construction and maintenance accessibility.

SUPERVISORY AND CONTROL SYSTEM

THE SUPERVISORY AND CONTROL STATION (FFWS DAM OFFICE) FOR THE SUB-SYSTEM IS LOCATED IN EACH DAM OFFICE. IT SUPERVISES AND CONTROLS THE TELEMETERING SYSTEM AND SERVES AS THE SUPERVISING CONTROL STATION FOR THE WARNING SYSTEMS WITHIN ITS AREA OF COVERAGE. IT ALSO PERFORMS THE FOLLOWING FUNCTIONS:

  1. Disseminates dam discharge warning;

  2. Disseminates flood warnings issued by PAGASA;

  3. Monitors the operating condition of the warning stations;

  4. Prints out the collected data for compilation and utilization in subsequent analysis;

  5. Analyses the collected data to forecast the water inflows in the reservoirs and implements the recommended reservoir operation program.

TELECOMMUNICATION SYSTEM

THE FFWS DAM OFFICE AND RAINFALL/WATERLEVEL GAUGING STATIONS ARE LINKED BY RADIO TELECOM NETWORK.

WARNING SYSTEM

The FFWSDO’s integrated and warning system includes the following:

  1. Fixed point warning stations categorized as Type-A and Type-B

  2. Mobile warning stations (vehicles) equipped with loud-speakers and portable radio telephones.

A Type-A warning station is equipped with a speaker and radio telephone. Generally, it is installed in the most densely populated area of each municipality with the area covered by each each FFWSDO. The Type-B warning station is equipped with speaker only and is installed in barangays located between the coverage of Type-A stations.

In area not reach by both fixed point warning stations, a warning vehicle equipped with a speaker and radio telephone is provided.

Discharge/Flood warning notices are transmitted from the Dam Offices to the municipal halls which serves as the center for the dissemination of warnings. All flood warning operation are undertaken in close coordination with the FFWS Dam Offices, PAGASA and other government agencies.

FLOOD FORECASTING AND WARNING OPERATION

FLOOD FORECASTING AND WARNING OPERATION INCLUDES A NUMBER OF INTERRELATED ACTIVITIES, EACH OF WHICH FORMS THE FOLLOWING INTEGRAL PART OF THE OPERATION:

  1. Collection of hydrometeorological data on real-time basis.

  2. Assessment of weather conditions affecting or expected to affect the reservoir catchment areas;

  3. Streamflow simulation and flood forecasting;

  4. Preparation and issuance of DICHARGE WARNINGS or FLOOD BULLETINS and FLOOD INFORMATION as the case may be; and

  5. Dissemination of discharge warnings of flood warnings /information to the local, municipal, and provincial government offices, disaster coordinating councils and the general public through the FFWS Center, FFWS Dam Offices, OCD, DPWH, NWRB and other government agencies as well as the print and broadcast media.

The Warning/Information on flood are divided into two n(2) groups, namely; Flood Bulletin and Flood Information.

Flood Bulletin is categorized into four (4) kinds of warning namely: Flood Outlook, Flood Advisory, Flood Warning and Critical Flood Warning. The PAGASA prepares and issues the corresponding Flood Bulletins at the exact time.

In the issuance of Flood Bulletins PAGASA uses three (3) assessment levels as guides, namely:

  1. ALERT W.L. - corresponds to such river discharge which will not cause flooding in the flood warning zone.

  2. ALARM W.L. - corresponds to such river discharge which will not cause substantial flooding in the cultivated land and residential areas.

  3. CRITICAL W.L. - corresponds to such river discharge that causes extensive flooding in cultivated land and residential areas.

Flood Information consists of two (2) types, namely: the Flood Warning Information and Flood Disaster Information.
The Flood Warning Information which is issued by PAGASA is the supplemental and periodical information on Flood Warning to the inhabitants in the flood warning zone.
The Flood Disaster Information is prepared and issued by the Office of Civil Defense (OCD) when a serious disaster due to flood is taking place in the flood warning zone.
The Flood Bulletins, Flood Warning Information and Flood Disaster Information will be disseminated to the government agencies concerned.
Dissemination of all bulletins and information related to flooding in the flood warning zones shall be the joint responsibility of PAGASA and concerned Dam Offices who are equipped with supervisory control of different warning facilities.

Projects
Decription Automation of Flood Early Warning System for Disaster Mitigation in Greater Metro Manila
Focal Points Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Ms. Sheila S. Schneider
Duration
Component KOICA
Donor
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Deployment of Early Warning System in Disaster Prone Areas (DEWS)
Focal Points Mr. Roy A. Badilla/Mr. Oskar D. Cruz
Duration
Component
Donor
PMO
Updates
Date Update Status
2017-10-14
  • IEC Tabuk City, Kalinga Personnel involved: OD Cruz, LClemente, NNievares, RMVergara
2017-10-22
  • Ocular Survey and Advance Coordination Meeting for IEC Region 7 Loboc and Tagbilaran City, Bohol Personnel involved: L. Clemente, J. Dalida, J. Lopez, A. Oris
  • Hydrographic Survey & Differential Leveling Region 5 (Albay, Sorsogon) Personnel involved: E. Caringal, C. Villalon, E. Bondoc, G. Cababa, J. Muyo
2017-11-05
  • Hydrographic Survey & Differential Leveling Region 5 (Camarines Norte and Camarines Sur) Personnel involved: M.T. Pajarillo, L. Lim, C. Villalon, J. Muyo, D. Villablanca
2017-10-27
  • DEWS 3rd Quarterly Meeting Dumaguete City, Negros Oriental Personnel involved: O. Cruz, N. Nievares, J. Lopez, J. Dalida, L. Blanco, J. Habaluyas
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding (opening of bids – 27 Oct. 2017) - MOA was already signed and coordination with the LGU of Cotabato City was undertaken for the final location of the station within the City Hall compound.
Decription Resilience and Preparedness towards Inclusive Development (RAPID) program under the Project Climate Twin Phoenix (PCTP)
Focal Points Focal Point: Mr. Maximo F. Peralta; Assistant Focal Point: Ms. Sheila S. Schneider
Duration 12 months
Component
Donor CCC
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Improvement of Capabilities to Cope with Natural Disasters caused by Climate Change (Rehabilitation of Equipment to Strengthen FFWS for Bicol River Basin)
Focal Points Focal Point: Mr. Berlin Mercado; Assistant Focal Point: Ms. Rosalie C. Pagulayan
Duration 2013-2018
Component
Donor Government of Japan (GoJ)
PMO
Updates
Date Update Status
2017-10-05
  • Conducted the Assessment/Evaluation of the stations to be demolished: Malabog Tower, Ligao Rainfall Station, Bato Rainfall & Water Level, Camaligan Tower and Generator House, Camaligan Rainfall and Water Level Station and Balongay Rainfall and Water Level. Please note that only Malabog and Balongay will be demolished as the lot will be utilized to construct the new tower and station, respectively.
2017-10-09
  • Monthly Meeting with Project Consultant and Contractor at Amihan Conference Room
Decription Development and Implementation of User-Relevant End-to-End Hydrological Forecast Generation and Application System for Disaster Mitigation in the Philippines
Focal Points Ms. Rhonalyn V. Macalalad
Duration 2014-2017
Component
Donor RIMES
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Japan’s Non-Project Grant Aid for Provision of Japanese SMEs Products 2012
Focal Points Ms. Rhonalyn V. Macalalad
Duration 2013-2014
Component
Donor GoJ/JICS
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Japan’s Non-Project Grant Aid for Provision of Japanese SMEs Products 2014
Focal Points Ms. Rhonalyn V. Macalalad
Duration 2013-2014
Component
Donor GoJ/JICS
PMO
Updates
Date Update Status
2017-10-17
  • Meeting for NPGA 2012 and 2014 by Japan International Cooperation System (JICS project) on at HMD Coordinate with JICS regarding the schedule of installation and training for Operation and Maintenance Coordinate with the contractor and field offices the schedule delivery and installation
Decription Strengthening Capacity of Comprehensive Data Management of Flood Forecasting and Warning System (FFWS) through Strategic Formulation of Hydrometeorological Information System (JFreeDAM Project)
Focal Points Ms. Rosalie C. Pagulayan
Duration 2016-2019
Component
Donor JICA
PMO
Updates
Date Update Status
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz
Duration 2013-2014
Component
Donor GoP
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz; On-site Focal Person: Mr. Socrates F. Paat, Jr.
Duration 2013-2014
Component
Donor GAA
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
2017-09-11
  • (FFWS) - Approval of MOA with DND
2017-09-20
  • (FFWS) - Processing for entry pass for site installation
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz; On-site Focal Person: Mr. Socrates F. Paat, Jr.
Duration 2013-2014
Component
Donor GAA
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz; Focal Person: Ms. Rhonalyn V. Macalalad
Duration 2013-2014
Component
Donor RIMES Project
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz; Focal Person: Ms. Margaret Bautista
Duration 2013-2017
Component
Donor Government of the Philippines
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz
Duration 2013-2014
Component
Donor GoP
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla Assistant Focal Point: Mr Edgar dela Cruz On-site Focal Person: Mr. Roy Badilla / Ms. R. Macalalad
Duration 2013-April 30,
Component
Donor Government of the Philippines
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz; On-Site Focal Person: Ms. Rhonalyn V. Macalalad
Duration 2013-2014
Component
Donor NPGA 2012
PMO
Updates
Date Update Status
2017-08-31
  • Establishment of Flood Forecasting and Warning System (FFWS) - Awarded August 31, 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Awarded August 31, 2017
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz; On-site Focal Person: Ms. Rhonalyn V. Macalalad
Duration 2013-2014
Component
Donor NPGA 2012
PMO
Updates
Date Update Status
2017-08-31
  • Establishment of Flood Forecasting and Warning System (FFWS) - Awarded August 31, 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Awarded August 31, 2017
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz;
Duration 2013-2014
Component
Donor GoP
PMO
Updates
Date Update Status
2017-10-27
  • DEWS 3rd Quarterly Meeting Dumaguete City, Negros Oriental Personnel involved: O. Cruz, N. Nievares, J. Lopez, J. Dalida, L. Blanco, J. Habaluyas
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding (opening of bids – 27 Oct. 2017) - MOA was already signed and coordination with the LGU of Cotabato City was undertaken for the final location of the station within the City Hall compound.
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz
Duration 2013-2014
Component
Donor GoP
PMO
Updates
Date Update Status
2017-10-01
  • Conduct Hydrographic survey (Pasig & Tullahan River and discharge measurement. (SSS, RIB & Arturo Samolde).
  • Installation of Staff Gauges for Eastwood Rodriguez, Tullahan Ugong and Rosario (Manalo) Bridge. (SSS, RIB & Arturo Samolde)
  • Computation of results of the hydrographic survey and preparation of reports (SSS)
  • Monitoring the status/progress of the installation of the monitoring equipment. (HMTS Group, Adrian Garcia and Leslie Madrazo)
  • Processing the procurement of the air conditioning unit for the command center.(Edgar dela Cruz)
  • Coordination meeting with the partner agencies (LA MESA and LGUs) on providing the required power supply for the installed monitoring equipment in their area including other concerns for the project. (BVM, RIB, SSS)
  • Coordinated with Ms. Regina Arquiza (KOICA representative) regarding the procurement of the Vehicle. (SSS)
  • Regular meeting with the EWS3 Project Manager Mr. Ji regarding the progress and other concern of the project. (RAB, BVM, RIB, SSS)
  • Facilitate the purchase of SIM Card for the monitoring stations (SSS & RIB)
  • Various activities related to the project. (HMD Personnel)
  • Submitted the result of the simulation of flood models (5, 25, and 100 YRP) to CCC
  • Processed the Rainfall Intensity results from Global Climate Models provided by CAD (c/o Ms.Thelma Cinco) as input to the flood models (Biased Correction and developed RIDF for Tacloban)
  • Simulation of flood model using projected Climate Change Scenarios
  • Preparation of Draft Technical Report
  • Preparation of initial design of MHEWSS
  • Project final activities
  • MOA Coordination and follow up DepEd/DPWH installation permit approved.
  • Establishment of Flood Forecasting and Warning System (FFWS) - Final sites to be surveyed (NPGA 2014)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation (75%) completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation -(40% completed)
  • Establishment of Flood Forecasting and Warning System (FFWS) - Installation completed – for final inspection
  • Establishment of Flood Forecasting and Warning System (FFWS) - On-going installation - 90% completed - Conduct of Stakeholders meeting for the newly-installed FFWS for Panay River Basin (to be undertaken in close coordination with Visayas-PRSD and Roxas Synoptic Station)
  • Establishment of Flood Forecasting and Warning System (FFWS) - For awarding Opening of Bids- 27 Oct. 2017
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed - Planning for Turnover and inauguration of the system
  • Establishment of Flood Forecasting and Warning System (FFWS) - For hydrological networking – table top survey - MOA finalization
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz
Duration 2013-2014
Component
Donor GoP
PMO
Updates
Date Update Status
2017-07-07
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Complete - Confirmation of sites for the monitoring stations (to be undertaken with MinPRSD)
  • Establishment of Flood Forecasting and Warning System (FFWS)
2017-11-29
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed
  • Establishment of Flood Forecasting and Warning System (FFWS) - Awarded August 31, 2017
Decription Establishment of FFWS Centers in 13 major river basin
Focal Points Project Focal Point: Mr. Roy A. Badilla; Assistant Focal Point: Mr Edgar dela Cruz; On-site Focal Person: Ms. Rhonalyn V. Macalalad
Duration 2013-2014
Component
Donor NPGA 2012
PMO
Updates
Date Update Status
2017-07-07
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Complete - Confirmation of sites for the monitoring stations (to be undertaken with MinPRSD)
  • Establishment of Flood Forecasting and Warning System (FFWS)
2017-11-29
  • Establishment of Flood Forecasting and Warning System (FFWS) - Project Completed
  • Establishment of Flood Forecasting and Warning System (FFWS) - Awarded August 31, 2017